Question No: 1

______ is defined as the probability of failure free operation of a computer program in a specified environment for a specified time.

► Software Reliability

► Software Usability

► Software Integrity

► Software Efficiency


Question No: 2

Schedule Performance Index SPI) is equal to

► BCWP / BCWS

► BCWP * BCWS

► BCWP + BCWS

► BCWP - BCWS


Question No: 3

The two objectives of a _____ are to identify problem areas within the work product and a checklist of action items.

► Review Issue List

► Formal Technical Reviews

► Informal Technical Reviews

► Testing


Question No: 4

It is noted that a/an ___________ review can be worse then no review at all

► Uncontrolled

► Controlled

► Intermediate

► Normal


Question No: 5

The Review participants SHOULD NOT be focused on _______.

► Weaknesses of the developer

► Time Lines

► Review agenda

► Work product


Question No: 6

The progress on a project at any given point in time can be calculated by:

► Adding all the BCWS till that point for all tasks

► Multiplying all the BCWS till That point for all task

► Adding BCWS and EVA for all task still that point

► Dividing all the BCWS till That point for al tasks


Question No: 7

Milestone represents:

► The defined target which you need to achieve

► A predictable risk that may hit the project

► An unpredictable risk that may project

► The Loss that organization may suffer due to risk



Question No: 8

If an error related to requirements is identified in testing phase, error will be considered an error of ________ phase.

► Requirement

► Design

► Code

► Testing


Question No: 9

________ involves rework, repair, and failure mode analysis of the product.

► Internal Failure Cost

► External Failure Cost

► Appraisal Cost

► Prevention Cost


Question No: 10

If:

E = Errors found before shipment

D = Errors found during operation

Then Defect Removal Efficiency (DRE) is equal to:

► DRE = E = / (E+D)

► DRE = E = * (E+D)

► DRE = E = + (E+D)

► DRE = E = - (E+D)


 "CS605 Quiz No. 1"(2)

Multiple Choice Question

6 February 2021



Question No: 1

BCWS is term used in Eamed Value Analysis it stands for _____.

► Budgeted Cost of Work Schedule

► Budgeted Cost of Whole System

► Beginning Cost of Whole System

► None of the given options


Question No: 2

______ states that 80% of the defects can be traced to 20% of its causes.

► Pareto Principle

► Fred Brooks Principle

► Kraul Principle

► D.Streeter Principle


Question No: 3

The basis principle for a review is that the focus should be on the _________..

► Product and not the producer

► producer and not the Product

► Profit to be gained

► Presentation ​Slide


Question No: 4

Many defect identified in few components at design level testing/review, a software development team should _____.

► Allocate good and extra resources at coding level to review these components thoroughly 

► Good achievement by designing team

► No need to allocated further resources at coding level to review these components

► Mission accomplished once good number of error/flaws identified level


Question No: 5

Milestone represents:

► The defined target which you need to achieve

► A predicable risk that may hit the project

► A unpredictable risk that may hit the project

► The Loss that organization may suffer due to risk


Question No: 6

______ a statistical technique is used to develop an overall indication of improvement in software quality.

► Error index

► Pareto Principle

► Quality Assurance

► Cost of Quality


Question No: 7

A model where Some errors are passed through to the next stem undebated such errors are said to have been______.

► Amplified

► Reduced

► Neutralized

► Multiplexed



Question No: 8

Earned Value Analysis (EVA) is a _____________ technique for assessing the progess of a project.

► Quantitative

► Subjective

► Qualitative

► Descriptive


Question No: 9

It is noted that a/an ________ review can be worse than no review at all.

► Uncontrolled

► Controlled

► Intermediate

► Normal


Question No: 10

FTR is a quality control activity performed by software enginers.it stands for:

► Formal Technical Review

► Formatted Technical Review

► Feasibility of Technical Requirement

► Fetched Technical Requirement



 "CS605 Quiz No. 2"

Multiple Choice Question

12 February 2021


Question No: 1

Legacy system migration however is a ________________ task and there are a number of risks involved that need to be mitigated.

► Crucial

► Simple

► Straight-forward

► Easy


Question No: 2

An Engineering Change Order (ECO) defines the change be made, its constraints and ________.

► Criteria for Review and Audit

► Removal of Change Request

► Approval by change control Board (CCB)

► Approval by Change Control Authority (CCA)


Question No: 3

A system is considered to be a legacy system if it has been in operation for _________ years. A legacy system has many components.

► Many

► Less then seven

► More than two

► Less than ten


Question No: 4

A major issue in requirements engineering is the rate at which requirements change once the requirements phase has "officially"________.

► Ended

► Approved

► Deleted

► Started


Question No: 5

The implemented requirement has been ______ through the selected approach, such as testing or inspection.

► Verified

► Deleted

► Approved

► Ignored



Question No: 6

According to a standish Group report, lack ______ is responsible for 13% of all project failures,

► User input

► Output

► Resources

► Development Plan


Question No: 7

 _________ is a quality assurance process used to reduce defects by avoiding or correcting mistakes in early design and development phases.

► Poka-Yoke

► Software Testing

► Software Change management

► Defect Removal


Question No: 8

According to Clemm, __________ allows the user to specify alternative forms of the system the selection of a appropriate versions.

► Configuration Management

► Process Management

► Quality Management

► Cost Management


Question No: 9

______ is the probability that a program is operating according to requirements at a given point in time.

► Availability

► Reliability

► Usability

► Security


Question No: 10

_____ enhance the product feature set by replacing a product with a newer version of the same product.

► Upgrade

► Re-Engineering

► Update

► Deployment


"CS605 Quiz No. 2"(2)

Multiple Choice Question

12 February 2021


Question No: 1

The equation to find out the Availability of software is:

► Availability = (MTTF / MTBF) x 100

► Availability = (MTTF / MTBF) / 100

► Availability = (MTTF + MTBF) / 100

► Availability = (MTTF - MTBF) / 100


Question No: 2 (rep)

According to a standish Group report, lack ______ is responsible for 13% of all project failures,

► User input

► Output

► Resources

► Development Plan


Question No: 3

The software reengineering is a _________ activity.

► Non-trivial

► Code

► Out dated

► Document



Question No: 4

A Software Requirement Specification (SRS) is traced if the ______ of requirements is clear.

► Origin

► Quality

► Standard

► Grammar


Question No: 5 (rep)

The implemented requirement has been ______ through the selected approach, such as testing or inspection.

► Verified

► Deleted

► Approved

► Ignored


Question No: 6 (rep)

A major issue in requirements engineering is the rate at which requirements change once the requirements phase has "officially"________.

► Ended

► Approved

► Deleted

► Started


Question No: 7

_______ are used by the development as a staging mechanism for functionality including regular builds.

► Internal releases

► External releases

► Major releases

► Feature releases


Question No: 8

________ are mechanisms that lead to prudential quality problem before it occur or its rapid detection it introduced.

► Mistake-Proofing

► Mistake-Profiling

► Mistake-Provoking

► Mismanagement-Proofing


Question No: 9

Version Control discusses about:

► How does an Organization control changes before and after installation released to a customer.

► How the resources will be assigned to tasks in work breakdown structure (WBS).

► How the test cases will be executed before deploying each release.

► How many feature will be included in software.


Question No: 10 (rep)

______ is the probability that a program is operating according to requirments at a given point in time.

► Availability

► Reliability

► Usability

► Security


"CS605 Quiz No. 2"(3)

Multiple Choice Question

12 February 2021


Question No: 1 (rep)

A major issue in requirements engineering is the rate at which requirements change once the requirements phase has "officially"________.

► Ended

► Approved

► Deleted

► Started


Question No: 2 (rep)

 _________ is a quality assurance process used to reduce defects by avoiding or correcting mistakes in early design and development phases.

► Poka-Yoke

► Software Testing

► Software Change management

► Defect Removal


Question No: 3 (rep)

________ are mechanisms that lead to prudential quality problem before it occur or its rapid detection it introduced.

► Mistake-Proofing

► Mistake-Profiling

► Mistake-Provoking

► Mismanagement-Proofing


Question No: 4

Which of the following is NOT one the tasks includes in Software Configuration Management.

► Test Case development

► Version Control

► Configuration Auditing

► Change Control


Question No: 5 (rep)

An Engineering Change Order (ECO) defines the change be made, its constraints and ________.

► Criteria for Review and Audit

► Removal of Change Request

► Approval by change control Board (CCB)

► Approval by Change Control Authority (CCA)


Question No: 6 (rep)

According to a standish Group report, lack ______ is responsible for 13% of all project failures,

► User input

► Output

► Resources

► Development Plan



Question No: 7 (rep)

The software reengineering is a _________ activity.

► Non-trivial

► Code

► Out dated

► Document


Question No: 8

____ error are most costly to fix.

► Requirement

► Design

► Implementation

► Testing


Question No: 9 (rep)

The equation to find out the Availability of software is:

► Availability = (MTTF / MTBF) x 100

► Availability ​= (MTTF / MTBF) / 10

► Availability ​= (MTTF + MTBF) / 10

► Availability = (MTTF - MTBF) / 100


Question No: 10

________ analysis is the first step in the reengineering process.

► Inventory

► Code

► Database

► Document


Best of Luck


YouTube Link:

https://www.youtube.com/c/VUEDUCATIONS

 

Facebook Page Link:

https://www.facebook.com/Vu-education-100866618120553/

 

WhatsApp Group Link:

https://chat.whatsapp.com/KEa5lP65yMdEF8BnmkC8jN


Tags

"CS605 quiz solution 2021, cs605. cs605 quiz 1 solve
cs605 quiz 2 solution 2021, cs605 quiz 1 solution 2021, cs605 quiz 2 solve,
vu education, virtual university, vu, vu past papers,"

Hashtag

#virtual university, #vu  #cs605quizsolution2021 #cs605quizsolution #cs605

#cs605quiz1solve #cs605quiz23solve #vueducation


Post a Comment

0 Comments